COMPLETED MEASURE J PROJECTS
OAKMONT HIGH SCHOOL
- GYMNASIUM ADDITION

| Construction Start Date: |
March
18, 2004 |
| Construction Completion Date: |
June 10, 2005 |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
581,832.00 |
|
| |
Developer Fee: |
$ |
115,074.33 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
123,872.75 |
|
| |
Construction: |
$ |
2,648,444.33 |
|
| |
Testing/Inspection: |
$ |
112,687.25 |
|
| |
Furniture/Equipment: |
$ |
0.00 |
|
| |
|
|
|
|
| Status: |
100% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
Final Audit Underway |
OAKMONT HIGH SCHOOL - PARKING LOT
| Construction Start Date: |
June 7, 2005 |
| Construction Completion Date: |
September 15, 2005 (estimate) |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
0.00 |
|
| |
Developer Fee: |
$ |
43,164.90 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
18,275.72 |
(preliminary) |
| |
Construction: |
$ |
620,482.93 |
(preliminary) |
| |
Testing/Inspection: |
$ |
4,406.25 |
(preliminary) |
| |
|
|
|
|
| Status: |
100% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
Not Started |
| |
|
The objectives for reconstruction
of the Oakmont parking lot were to prevent liability and injury
from hazardous pavement, to increase parking spaces, and to improve
traffic flow. Another goal was to accommodate the campus need
for more classrooms due to a projected increase of 338 students
from the previous year. Improvements involved modification of
concrete landscape islands, reconfiguration of the parking stall
layout, and construction of new concrete islands. The project
was substantially completed, allowing for a functional parking
lot, by the start of the 2005 school year.
On the first day of school the parking lot was
a scene of chaos. Freshmen parents unsure of where to drop off
students combined with drivers unfamiliar with the changes created
a traffic nightmare. But with all new things, it only took time
to adjust. Assitant principal Mr. Greg O'Meara stated, "During
the first week, it took over 30 minutes to clear the parking
lot after school. After a few weeks, it took only 20 minutes."
As time went on, teachers and students also noticed subtle improvements.
"The parking lot shows a better utilization of space in
front and the flow of traffic is smoother than last year," declares
Mrs. Young. Junior Fiona Joy agrees, "It seems that the
parking lot is clearing out pretty fast; it's not a major difference
from last year, but it is noticeable." It appears that the
general consensus at Oakmont is that the parking lot modifications
have been a success.
rev. 10/18/05 |
ROSEVILLE HIGH SCHOOL - PERFORMING ARTS BUILDING

| Construction Start Date: |
April 15, 2004 |
| Construction Completion Date: |
August 1, 2005 |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
1,343,697.00 |
|
| |
Developer Fee: |
$ |
240,061.68 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
574,147.03 |
(preliminary) |
| |
Construction: |
$ |
5,957,168.24 |
(preliminary) |
| |
Testing/Inspection: |
$ |
386,480.50 |
(preliminary) |
| |
Furniture/Equipment: |
$ |
359.91 |
(preliminary) |
| |
|
|
|
|
| Status: |
100% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
Pending |
GRANITE BAY HIGH SCHOOL - TWO STORY CLASSROOM BUILDING

| Construction Start Date: |
September 29, 2003 |
| Construction Completion Date: |
November 15, 2004 |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
2,309,073.00 |
|
| |
Developer Fee: |
$ |
399,768.48 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
265,584.88 |
|
| |
Construction: |
$ |
3,762,686.10 |
|
| |
Testing/Inspection: |
$ |
127,464.15 |
|
| |
Furniture/Equipment: |
$ |
91,544.35 |
|
| |
|
|
|
|
| Status: |
100% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
Final Audit Underway |
ROSEVILLE HIGH SCHOOL - TWO STORY SCIENCE BUILDING

| Construction Start Date: |
September 29, 2003 |
| Construction Completion Date: |
November 15, 2004 |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
3,192,936.00 |
|
| |
Developer Fee: |
$ |
2,358,157.03 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
518,565.59 |
|
| |
Construction: |
$ |
6,117,867.86 |
|
| |
Testing/Inspection: |
$ |
127,794.03 |
|
| |
Furniture/Equipment: |
$ |
104,325.55 |
|
| |
|
|
|
|
| Status: |
100% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
Final Audit Underway |
WOODCREEK HIGH SCHOOL - FIELD IMPROVEMENTS

| Construction Start Date: |
May 24, 2005 |
| Construction Completion Date: |
September 8, 2005 (estimate) |
| |
|
|
|
|
| Funding: |
Measure J: |
$ |
|
|
| |
State: |
$ |
0.00 |
|
| |
Developer Fee: |
$ |
144,380.09 |
|
| |
|
|
|
|
| Cost: |
Planning: |
$ |
79,519.30 |
|
| |
Construction: |
$ |
1,161,564.99 |
|
| |
Testing/Inspection: |
$ |
3295.80 |
|
| |
|
|
|
|
| Status: |
90% Complete |
|
|
|
| |
|
| Office of Public School Construction
(OPSC) Audit Status: |
No Audit |
|